TL;DR: all GREEN.
Test Pilot
-
Q3 OKRs are set and have been migrated into Airtable.
-
Had a confounding issue where the majority of images on the dev server were missing. Tied up a chunk of the team for the better part of a day.
-
GitHub tells me that from 2018-08-10 through 2018-08-17
-
Excluding merges, 29 authors have pushed 9 commits to master and 71 commits to all branches.
-
On master, 8 files have changed and there have been 4,526 additions and 4,516 deletions.
-
Of those 80 commits, 59 were made by folks not on the Test Pilot team.
Cloud Storage
-
Shield Study: launched 2018-06-28.
-
End date for the study was 2018-07-16. It is self-expiring and users are being unenrolled.
-
Preliminary findings were presented 2018-07-23.
-
8800 respondents
-
97% response rate
-
Google Drive, then Dropbox, then Microsoft One Drive, then iCloud.
-
Final report was expected 2018-08-03; it is in progress, but behind schedule.
-
Determining next steps for this project, including what team should own this feature.
Color
-
Continuing to work on custom backgrounds in Color, just got drag & drop working.
-
Adding pagination to pre-set themes.
-
Working on addressing performance issues; one significant bug was identified.
-
Working through new designs and use cases so this can eventually replace Personas Plus.
-
Red-lined design spec is being completed.
- No progress this week due to PTO.
Laserlike, aka Advance
- Launched 2018-08-07.
Lockbox
-
iOS
-
FxA oAuth work landed.
-
Version 1.2 on track to launch late August.
-
Test Pilot/Lockbox retrospective scheduled for mid-August.
-
Android
-
UX designs complete.
-
Milestone planning is behind schedule.
-
Development work will start early September.
Notes
-
Planning for potential graduation of Notes out of Test Pilot to Alex Davis’ team.
-
Figuring out what remaining actions need to be instrumented (e.g., how many users are on both desktop and mobile, users who sync, etc.).
-
New log in flows tested on three different mobile devices.
-
QA has given a Yellow - Ship it Conditionally flag.
-
No blockers, but several bugs remain.
-
Gathering Google Play store feedback to see how different/similar volume and type of feedback.
-
Feedback from surveys rolling in: checklists are most requested feature.
Send
-
Emily’s intern presentation was 2018-08-07; her last day was 2018-08-10.
-
Working on integrating Android and web with FxA.
-
Tons of help from Notes team.
-
Work started on authenticated apis (currently on hold until scope available).
-
Split mobile UI spec into separate tickets so work can get started: 13 issues in Android project.
-
Send Android ported to choo.
-
UX work on Android landed.
-
New designer on board; doing pass on mobile designs.
-
Planning started for potential beta launch when 63 hits beta.
Side View
-
~6500 users.
-
Led to ~12k+ more Test Pilot installs.
-
20K+ referrals from a snippet that pointed to the Mozilla blog that was posted 2018-07-10.
-
Working to get Side View into Shield; PHD written and submitted for review.
-
Tentatively scheduled for Shield review 2018-08-08.
-
Engineering work (metrics, onboarding) needed for Shield study.
TBD
-
Team is working on a new concept.
-
Preliminary max/diff survey is live.
-
Beginning discussions with outside teams to discuss overlap, plans, etc.