TL;DR: all GREEN.
Test Pilot
-
Q4 OKRs are being iterated through; meeting next week to finalize.
-
Production release on 2018-09-17.
-
GitHub tells me that from 2018-08-31 through 2018-09-07
-
Excluding merges, 6 authors have pushed 9 commits to master and 11 commits to all branches. On master, 26 files have changed and there have been 3,656 additions and 3,373 deletions.
-
Of those authors, 3 were external contributors (work is slowing down on the platform, as planned).
Cloud Storage Shield Study
-
Determining next steps for this project, including what team should own this feature.
-
Final report published internally, blog post forthcoming.
Color
-
Dashboard for up-to-date metrics in place.
-
UI cleanup: static theme improvements, theme image previews, final refinement.
-
Proposal for simplifying and merging all 3 Firefox theming mechanisms into one.
-
Agreement w/ddurst’s team about date for transferring ownership of Color.
Email Tabs
-
Proposed launch date is early November, working with Marketing to narrow down a date.
-
GA property set and merged.
-
10 items remaining in MVP launch milestone.
-
Will hand over to QA next week for testing.
Laserlike, aka Advance
-
Launched 2018-08-07.
-
Experiment running.
Notes
- Product-based discussions for transfer of Notes out of Test Pilot to Alex Davis’ team.
Price Alerts
-
Held preliminary kickoff meeting with Price Alerts team.
-
Upcoming meetings to determine schedules, tasks, etc.
-
Preliminary launch date planned in early November. Working with Marketing to finalize.
Send
-
In progress:
-
FxA mobile integration slipping one week, until beginning of Q4.
-
Decision to have Ops host beta release.
-
Will have discrete GA for beta site.
-
Final URL for beta site decided.
-
Testing begins this week.
-
Release delayed until 64 goes live due to streams API dependencies.
-
This will enable us to pick up the new Firefox branding.
Side View
-
Working to get Side View into Shield; PHD written.
-
Shield PHD reviewed 2018-08-08.
-
Engineering work in progress for Shield study.
-
Design in progress for Shield study.
-
Goal: Q4 in Shield.
-
Acceptance criteria in progress for getting Side View on AMO.